Substation NOF in Minnesota has 1 tracked interconnection feeder, 1 flagged capacity-constrained, carrying 50 active applications as of June 2026. The longest estimated wait among them is about 28 years.
Across 1 tracked feeder — as of June 2026
50
active applications (all feeders)
1
capacity-constrained feeders
28yrs
longest estimated wait